Roads continue to be updated in and around Dell Rapids this spring and summer.
10th street was just recently closed for completion. Removals and grading work is now beginning for 10th Street. Curb and guttering will take place in the next few weeks, and the asphalting of the street will follow. The sidewalk install and grading of the yard behind the curb will be the last steps. Substantial completion date for the 10th Street project has been set for June 10th.
City Administration was informed by the South Dakota Department of Transportation that the Hwy 115 bridge will be opened by May 1st. That is also the same day that Interstate 29 overpass is scheduled to be closed for that project. During the last regular meeting, the Dell Rapids City Council approved city administration to arrange a meeting with LG Everist, the I-29 project contractor, and the SD DOT to discuss a temporary truck route south through on Garfield Ave to Quartzite St.